Riverside Hall Lighting Project

This summer, contractors and Facilities Management will be updating lighting in Riverside Hall. All hallways and labs will have new energy efficient lighting installed.

The project is scheduled to take place from June 14, 2024 to August 5, 2024, proceeding one floor at a time.

Riverside Hall floors will be inaccessible to any employee or student during the periods noted below.

The main doors on the East and West sides of Riverside Hall will remain accessible, except during the brief time needed to install new fixtures just inside the entrances, which will be caution-taped off. The elevators will remain operational throughout the project.

For assistance, you can reach the Dean’s Office via email at ecs-doassist@csus.edu or through Teams.

Schedule of RVR Floor Closures

Updated 6/28/24

  • 1st Floor - Completed
  • 2nd Floor - Completed
  • 6/24/2024 to 7/01/2024 - 5th Floor
  • 7/08/2024 to 7/24/2024 - 3rd Floor
  • 7/22/2024 to 8/02/2024 - 4th Floor