Chapter 17 key terms

 

A-0-A   activity-on-arrow - a network diagram convention in which arrows designate activities.

 

A-0-N   activity-on-node- a network diagram convention in which nodes designate activities.

 

Activities -  steps in the project that consume resources and/or time.

 

Arrow   indicates the direction of flow in the precedence diagram.

 

 Beta distribution-   in PERT with three time estimates for completion of an activity, the distribution form governing the calculation of the means and variances of activity completion times.

 

CPM (Critical Path Method) - PERT and CPM were developed separately at about the same time in the late 1950s. Both techniques are concerned with integrating and managing a project consisting of a number of different tasks.

 

Crash -  to shorten an activity.

 

Crash time-   the completion-time estimate for an activity resulting from crashing it.

 

Critical activity-   an activity on the critical path.

 

Critical path-  the path in a network diagram that takes the longest time for completion.

 

Deterministic- time estimate   a single time estimate for an activity, with no alternative estimates or probability distribution of estimates.

 

Event-   the starting and finishing of activities, designated by nodes in the AOA convention.

 

Gantt chart-   visual aid used for scheduling simple projects.

 

 Independence-   the assumption that activity duration times are not related to each other and that each activity is on only one path.

 

Most likely time-   the most probable length of time that will be required.

 

 Network- (precedence) diagram -  diagram of project activities that shows sequential relationships by the use of arrows and nodes.

 

Optimistic time-   the length of time required under optimal conditions; the shortest time.

 

Path-   a sequence of activities that leads from the starting node to the finishing node.

 

PERT- (Program Evaluation and Review Technique)   see CPM.

 

Pessimistic time-   the length of time required under the worst conditions; the longest time.

 

Predecessor -  for two activities joined at a node, the predecessor is the one that precedes, and the successor is the one that follows.

 

Probabilistic -time estimates   estimates of times that allow for variation.

 

 Project -  unique, one time operations designed to a specific set of objectives in a limited time frame.

 

Project champion -  people within the company who promote and support the project.

 

 Project life cycle-   the definition, planning, execution, and termination of the project.

 

Risks -  the danger of occurrences that can have undesirable consequences, such as delays or increased costs.

 

 Slack -  the allowable slippage for any activity; it is the difference between the length of a given path and the length of the critical path.

 

Work breakdown structure-   a hierarchical listing of what must be done during a project.